A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
Home
Agile
A team finishes developing all of their Stories in the first six days of the Iteration, tests them...
+4
votes
asked
Jul 31, 2019
in
Agile
by
sheetalkhandelwal
edited
Jan 30, 2021
by
SakshiSharma
A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?
#agile-development
#agile-methodology
#scaled-agile
#scaled-agile-framework
#agile-process
#agile-vs-scrum
#agile-methodologies
#what-is-safe
#safe-agile
#safe-methodology
Please
log in
or
register
to answer this question.
1
Answer
+3
votes
answered
Jul 31, 2019
by
Robindeniel
edited
Jan 30, 2021
by
SakshiSharma
They are waterfalling the Iteration
...