Which two (2) things does the Development Team not do during the first Sprint?

Deliver an increment of potentially shippable functionality. 

Nail down the complete architecture and infrastructure.  

Develop and deliver at least one piece of functionality. 

Develop a plan for the rest of the project. 

▼ Show 1 Answer

0 votes
by

Option- B & D

Nail down the complete architecture and infrastructure.  

Develop a plan for the rest of the project. 