in PMP by
Q:
All of the following tools and techniques are part of processes in the

Executing process group except:

a Performing activities in accordance with the project management plan.

b Managing changes to the deliverables.

c Completing the work in accordance with the defined quality framework and

specification.

d Coordinating people and resources.

1 Answer

0 votes
by
The best answer is B

 i Managing changes is part of Integrated Change Control; this is part of

the Monitoring and Controlling process group.

 ii The Executing process group consists of those processes performed

to complete the work defined in the project management plan to

satisfy the project specifications.

 iii An output from Integrated Change Control is updates to the project

management plan to incorporate approved changes.
Click here to read more about Loan/Mortgage
Click here to read more about Insurance

Related questions

0 votes
asked Oct 1, 2020 in PMP by SakshiSharma
0 votes
asked Sep 14, 2020 in PMP by SakshiSharma
+1 vote
asked Feb 19 in Linux by SakshiSharma
0 votes
asked Feb 10, 2020 in Big Data | Hadoop by miceperry
0 votes
asked Nov 24, 2020 in Agile by sharadyadav1986
...