in Agile by
Q:

What does a burndown chart measure?

a. Schedule time against expected budget

b. Return on investment

c. How quickly activities move between stations

d. The amount of work still to be done against the time allocated

Related questions

0 votes
asked Sep 13, 2020 in Agile by Robindeniel
0 votes
asked Sep 17, 2020 in Agile by SakshiSharma
0 votes
asked Sep 16, 2020 in Agile by Robindeniel
+1 vote
asked Feb 14, 2020 in Agile by matthenary
+1 vote
asked Feb 8, 2020 in Agile by rahuljain1
...