What is the relationship between Product Backlog and Sprint Backlog?

 The Product Backlog is equal to the Sprint Backlog.

 The Product Backlog is a subset of the Sprint Backlog.

 The Sprint Backlog is a subset of the Product Backlog.

 The Sprint Backlog is owned by the Product Owner

1 Answer

0 votes
by
Answer- C

The Sprint Backlog is a subset of the Product Backlog.