During a Sprint Planning Meeting, the Product Owner

 Determines how the Team accomplishes its work

 Divides selected stories in to specific tasks

 Presents stories that he/she would like the Team to complete during the Sprint

 Decides how many stories will be delivered by the end of the Sprint

1 Answer

0 votes
by
Answer-  Presents stories that he/she would like the Team to complete during the Sprint