Which statement best describes the Sprint Review?

 It is a review of the team's activities during the Sprint. 

 It is when the Scrum Team and stakeholders inspect the outcome of the Sprint and figure out what to do in the upcoming Sprint. 

 It is a demo at the end of the Sprint for everyone in the organization to provide feedback on the work done. 

 It is used to congratulate the Development Team if it did what it committed to doing, or to punish the Development Team if it failed to meet its commitments.

1 Answer

0 votes
by
It is when the Scrum Team and stakeholders inspect the outcome of the Sprint and figure out what to do in the upcoming Sprint.