You are executing a project, and you have come to know that project information has to be retained for a period more than the project duration due to regulatory requirements. What should you do?

A. Just keep the backup of information as the customer would be aware of the regulatory requirement

B. Communicate to the customer that information has to be retained beyond the project duration with reason.

C. No need to communicate to the customer as it is a regulatory requirement

1 Answer

0 votes
by

B. Communicate to the customer that information has to be retained beyond the project duration with reason.

...