0 votes
in Other by

A few days after the sprint planning, the Product Owner finds that it makes sense to develop another new functionality. Which two of the following statements are correct?

A. The Developers will add the new item to the Sprint Backlog

B. The Product Owner can add the new item in the product backlog in the next sprint planning. Then the Product Owner can bring that up for the developers selection.

C. If the Developers agree, the Product Owner can swap an existing functionality in the current sprint, for the new functionality.

D. The Developers should obtain the Scrum Master’s approval to add this to the Sprint Backlog

1 Answer

0 votes
by

B. The Product Owner can add the new item in the product backlog in the next sprint planning. Then the Product Owner can bring that up for the developers selection.

C. If the Developers agree, the Product Owner can swap an existing functionality in the current sprint, for the new functionality.

...