If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?
0
votes
asked
Oct 31, 2022
in
Agile
by
Robin
If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?
agile
pmp
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Oct 31, 2022
by
Robin
Risk value
Present value
Expected monetary value
Contingency budget
EMV = .9 X $ 10,000 = $ 9,000
...