Login
Remember
Register
Ask a Question
An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed.
0
votes
asked
Oct 31, 2022
in
Agile
by
Robin
An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?
agile
pmp
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Oct 31, 2022
by
Robin
Additional resources using the contingency fund
Escalation approval to use contingency funding
Team overtime to meet schedule
Corrective action based on causes
...