in Agile by
Q:

1 Answer

0 votes
by

Program Increment (PI) is a timebox during which an Agile Release Train (ART) delivers incrementalvalue in the form of working, tested software and systems. PIs are typically 8 – 12 weeks long. The most common pattern for a PI is four development Iterations, followed by one Innovation and Planning (IP) Iteration.