Who is responsible to measure the Project’s performance?
Home
Agile
Who is responsible to measure the Project’s performance?
asked
Dec 5, 2020
in
Agile
by
SakshiSharma
Who is responsible to measure the Project’s performance?
a. The Scrum Master
b. The Delivery Manager
c. The Product Owner
d. The Development Team
e. The Scrum Team
#agile-project-performance
#agile
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Dec 5, 2020
by
SakshiSharma
c. The Product Owner
Reasoning
Being the customer’s voice, it is the Product Owner’s responsibility to measure the Project’s and Release performance and see if the team is on track to complete the project on time.
...