Which of the following represent a discretionary dependency?
a Not starting design until all of the approvals have been received.
b Waiting the specified 72 hours before stripping formwork from a newly poured concrete slab.
c Applying a start-to-start link between two tasks in a PDM network.
d Applying a lag of 4 days between two tasks.