Which of the following represent a discretionary dependency?

a Not starting design until all of the approvals have been received.

b Waiting the specified 72 hours before stripping formwork from a newly poured concrete slab.

c Applying a start-to-start link between two tasks in a PDM network.

d Applying a lag of 4 days between two tasks.

2 Answers

0 votes
by
The best answer is A
0 votes
by
The best answer is A

Not starting design until all of the approvals have been received.