The project charter has all of the following characteristics except:
a Its primary use is to authorise the start of a project or phase.
b It provides the project manager with authority to apply resources and
expend money on project activities.
c Its primary use is to request bids or proposals for the work it defines.
d The project charter can be created by the person external to the project, responsible for the authorisation of the work, or that person can delegate the creation of the project charter to the project manager.