The risks in the Risk Register are updated as a part of each of the following
processes:
a Plan Risk Management, Identify Risks, and Perform Qualitative Risk
Analysis.
b Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk
Analysis and Monitor Risks.
c Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan
Risk Responses, Implement Risk Responses and Monitor Risks.
d Plan Risk Management, Identify Risks, Plan Risk Responses, and Monitor
Risks.