A procurement audit will consider all of the following except:
a The changes in market conditions between the contract date and the
current time.
b Any successes or failures in the process that warrant recognition.
c The complete procurement process from initial planning through to closure
of the procurement.
d Any lessons learned that can be applied to future procurement processes.