Integrated Change Control includes all of the following tools and techniques except:
0
votes
asked
Sep 14, 2020
in
PMP
by
SakshiSharma
Integrated Change Control includes all of the following tools and
techniques except:
a Project management plan updates.
b Expert judgement.
c Meetings.
d A change control board to approve or reject changes.
#pmp-tools
#tools-techniques
#pmp
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Sep 14, 2020
by
Robindeniel
The best answer is A
i Project plan updates are an output from Integrated Change Control.
ii Expert judgement and the change control meetings, of the change
control board are the defined tools and techniques for this process.
...