James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?
+5
votes
asked
Jul 29, 2019
in
Agile
by
sheetalkhandelwal
edited
Jan 30, 2021
by
SakshiSharma
James is a Product Owner. It is day seven of the Iteration and his team tells him that they may miss their Iteration commitment. What should James do?
#agile-development-methodology
#agile-training
#agile-software
#agile-process
#agile-vs-scrum
#agile-methodologies
#scaled-agile-framework
#safe-agile
#agile
definition
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Aug 5, 2019
by
anonymous
Support pulling a Story that has not been started
...