What is the main purpose of a Sprint Review? Choose the correct option

1) For Stakeholders to "hold the Team's feet to the fire" - to make sure something is produced during the Sprint

2)  For the Team to review their work and to determine what is needed to complete the next set of backlog items

3)  For the Product Manager to be able to show progress to the Stakeholders

4)  For Stakeholders to review what the Team has built and to give input on what to do next

1 Answer

0 votes
by
Correct option is

4. For Stakeholders to review what the Team has built and to give input on what to do next