The timebox for the completing Sprint Planning meeting is

 4 hours.

 8 hours for a monthly Sprint, proportionately less for shorter Sprints.  

 16 hours

 20 hours

1 Answer

0 votes
by
8 hours for a monthly Sprint, proportionately less for shorter Sprints.