When a Development Team determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?

 The Scrum Master, Project Manager and Development Team. 

 The Product Owner and Development Team.  

 The Product Owner and all stakeholders.

 The Development Team.

1 Answer

0 votes
Nov 17, 2019
The Product Owner and Development Team.