All of the following are ALWAYS inputs to the risk management process EXCEPT:

1 Answer

0 votes
by (14.5k points)

Historical information

Lessons learned

Work breakdown structure

Project status reports

Project Status report can be an input to risk management. However, when completing risk management for the first time, you wouldn’t have the project status report yet. Therefore, the project status report is not always an input to risk management.