Which one of the following statements is true for Agile projects?

a) All project stakeholders should attend every requirements workshop

b) Retrospectives are only run at the end of a project

c) It is best if project manager facilitates the project’s workshops

d) A facilitator will manage the structure of a facilitated workshop

1 Answer

0 votes
Apr 24

d) A facilitator will manage the structure of a facilitated workshop