in Agile by
Q:
What is the approach that Scrum encourages when a Team determines it will be difficult to deliver any value by the end of a Sprint?

 Together with the Product Owner, focus on what can be done and identify a way to deliver something valuable at the end of each Sprint.

 Immediately escalate to Senior Management.

 Suggest the Product Owner to abnormally terminate the Sprint.

 Extend the Sprint by a few days to accommodate the extra work.

▼ Show 1 Answer

0 votes
by
Together with the Product Owner, focus on what can be done and identify a way to deliver something valuable at the end of each Sprint
Agile
Learn More with Madanswer

Related questions

0 votes
asked Jan 19, 2020 in Agile by rajeshsharma
...