Q: The CEO asks the Development Team to add a "very important" item to the current Sprint.What should the Development Team do?

 Add the item to the current Sprint without any adjustments.

 Add the item to the current Sprint and drop an item of equal size.

 Add the item to the next Sprint.

 Inform the Product Owner so that he/she can work with the CEO.

1 Answer

Nov 17, 2019
Inform the Product Owner so that he/she can work with the CEO.