Q:
saf

► Click here to show 1 Answer

0 votes
by
Normalize story point estimation:

Find a small story that would take about a half-day to develop and a half-day to test and validate, and call it a “one”

Estimate every other story relative to that “one”

Establish velocity before historical data exists:

For every full-time developer and tester on the team, give the team 8 points (adjust for part-timers)

Subtract one point for every team member vacation day and holiday in the iteration
by

The team members assess their availability, acknowledging time off and other potential duties