When is a Sprint over?

A. When the Product Owner says it is done.

B. When all Product Backlog items meet their definition of “Done”.

C. When all the tasks are completed.

D. When the time-box expires.

1 Answer

0 votes
by

Correct Answer: D

Explanation: Sprints are fixed length events of one month or less to create consistency. A new Sprint starts immediately after the conclusion of the previous sprint.