Risk tolerance is determined in order to help:

The team ranks the project risks.

The project manager estimates the project.

The team schedules the project.

Management knows how other managers will act on the project.

1 Answer

0 votes
by
If you know the tolerance of the stakeholders, you can predict how they might react to different situations and risk events. This information can help assign levels of risk on each work package activity.