If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?
Home
Agile
If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000,...
0
votes
asked
Oct 31, 2022
in
Agile
by
Robin
If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?
agile
pmp
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Oct 31, 2022
by
Robin
Risk value
Present value
Expected monetary value
Contingency budget
EMV = .9 X $ 10,000 = $ 9,000
Your comment on this answer:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Related questions
0
votes
Q: If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?
asked
Oct 31, 2022
in
Agile
by
Robin
pmp
agile
risk
0
votes
Q: An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed.
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
0
votes
Q: The risk will be identified during which risk management process(es)?
asked
Oct 31, 2022
in
Agile
by
Robin
agile
risk
pmp
+1
vote
Q: During which risk management process is a determination to transfer a risk made?
asked
Oct 31, 2022
in
Agile
by
Robin
risk-management
agile
pmp
+1
vote
Q: A project manager is quantifying risk for her project
asked
Oct 31, 2022
in
Agile
by
Robin
pmp
agile
+1
vote
Q: You are finding it difficult to evaluate the exact cost impact of risk. You should evaluate on a(n) :
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
0
votes
Q: Assuming that the ends of a range of estimates are +/- 3 sigma from the mean, which of the following range estimates involves the LEAST risk?
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
0
votes
Q: Risk tolerance is determined in order to help:
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
0
votes
Q: All of the following are ALWAYS inputs to the risk management process EXCEPT:
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
0
votes
Q: During a bidder conference, you see that one bidder is your close friend. What should your next step be?
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
...