Home
Recent Q&A
Java
Cloud
JavaScript
Python
SQL
PHP
HTML
C++
Data Science
DBMS
Devops
Hadoop
Machine Learning
Azure
Blockchain
Devops
Ask a Question
An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed.
Home
Agile
An accepted deadline for project approaches. However, the project manager realizes only 75% percent...
0
votes
asked
Oct 31, 2022
in
Agile
by
Robin
An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?
agile
pmp
Please
log in
or
register
to answer this question.
1
Answer
0
votes
answered
Oct 31, 2022
by
Robin
Additional resources using the contingency fund
Escalation approval to use contingency funding
Team overtime to meet schedule
Corrective action based on causes
Related questions
0
votes
Q: If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?
asked
Oct 31, 2022
in
Agile
by
Robin
pmp
agile
risk
0
votes
Q: If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
+1
vote
Q: Being assigned as a project manager, you noticed during project execution that conflicts arise in the team on both technical and interpersonal levels. What is an appropriate way of handling conflicts?
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
+1
vote
Q: A project manager is quantifying risk for her project
asked
Oct 31, 2022
in
Agile
by
Robin
pmp
agile
0
votes
Q: When estimating time for activities, a Project Manager should:
asked
Oct 31, 2022
in
Agile
by
Robin
project-management
pmp
agile
0
votes
Q: The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
+1
vote
Q: An earthquake damaged your construction project. Your contractor says that he cannot fulfill the terms of the contract due to a specific clause you both had signed the contract. He is referring to the:
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
+1
vote
Q: You are running a project to engineer and implement a set of business processes and a software solution for customer relationship management.
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
0
votes
Q: The Expected Monetary Value for the project is:
asked
Oct 31, 2022
in
Agile
by
Robin
agile
pmp
+1
vote
Q: When control charts are used, outliers are:
asked
Oct 31, 2022
in
Agile
by
Robin
control-charts
agile
pmp
...