An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

1 Answer

0 votes
by
Additional resources using the contingency fund

Escalation approval to use contingency funding

Team overtime to meet schedule

Corrective action based on causes