What is a Sprint Planning Meeting, Sprint Review Meeting and Sprint Retrospective Meeting?

1 Answer

0 votes
by
Sprint Planning Meeting: In this meeting, the discussion takes place about features and product backlog items (user stories) that are important to the team. This meeting is usually attended by the product owner, Scrum Master and Scrum Team. It is a weekly meeting and usually lasts for about an hour.

Sprint Review Meeting: In this meeting, the Scrum team gives a demonstration of the product. After this, the product owner determines which items completed and which are not completed. He also adds some additional items to the product backlog on the basis of feedback from customers or stakeholders. Its main aim is to inspect the product being created in the sprint and modify it if required.

Sprint Retrospective Meeting: This meeting takes place after the Sprint planning meeting. In this meeting, the Scrum team meets again to inspect itself and discuss the past mistakes, potential issues and methods to resolve them. Main aim of this meeting is to improve the development process. This meeting lasts for about 2-3 hours.

Related questions

0 votes
asked Jun 9, 2023 in Agile by Robin
0 votes
asked Apr 21, 2021 in Agile by rajeshsharma
...