Which one of the following statements is correct regarding acceptance of any deliverables on an Agile Project?

a) The team should allow only senior managers to sign off deliverables

b) The team should get acceptance of project deliverables from the appropriate stakeholders at least at the end of every timebox / iteration

c) The team should get acceptance of project deliverables from the users during a UAT phase at the end of the project

d) Acceptance of any particular deliverable on the project is gained from all stakeholders at the same time.

1 Answer

0 votes
Apr 24

b) The team should get acceptance of project deliverables from the appropriate stakeholders at least at the end of every timebox / iteration