How should work be allocated to the team in an Agile project?

a) The Project Leader should give tasks to individuals to create challenges for them

b) Tasks should be randomly allocated using Planning Poker

c) Team members should self-select tasks

d) The biggest tasks should be done by the Project Leader themselves

► Click here to show 1 Answer

0 votes
by

c) Team members should self-select tasks