The product owner is leading the Team to decide which features they should include in the Sprint Backlog first. They decide to select the most important features by identifying which features will bring the most benefits if implemented, as well as the penalty incurred if not implemented, on a relative scale of 1 to 9. This can best be described as:

a) Relative prioritization

b) Value base computation estimate

c) Must-have prioritization

d) Darwinism estimation

1 Answer

0 votes
by

a) Relative prioritization