In Agile development, when a developer estimates a story point by gauging the amount of effort required to complete a task based on the amount of time she will have to focus exclusively on the task, with no interruptions, what estimate unit is she using?

a) Ideal Time

b) Velocity

c) Alternative Time

d) Time box

1 Answer

0 votes
by
a) Ideal Time