in Agile by
For one of your product, optimal cost of change (Coc) was estimated to be 100 story points but at the end of the iteration actual C0C was found to be 200 story points. What is the Technical debt that your project had encountered (if any)?

a) None. “Velocity” the great equalizer will take care of Technical debt.

b) None. Your developers will work extended hours to pay back the Technical debt in next iteration so it can be ignored for now.

c) 100 Story points

d) 200 Story points

1 Answer

0 votes
by
c) 100 Story points