in Agile by
Q:
What activities are a part of Product Backlog Refinement?

a. Estimate the Product Backlog Items

b. The ordering of the Product Backlog Items

c. Creating the Definition of Done

d. Creation of tasks

e. Brainstorming on the Product Backlog Items

1 Answer

0 votes
by

a. Estimate the Product Backlog Items

 

b. The ordering of the Product Backlog Items

e. Brainstorming on the Product Backlog Items

Reasoning

Product Backlog Refinement is an activity where the entire team sits together and brainstorm around the backlog items. The backlog items are refined and the details are added to them.

During the meeting, the Product Backlog items are ordered based on their priority. Once the Product Backlog items have been refined, the Development Team members estimate the Product Backlog Items.

Click here to read more about Agile
Click here to read more about Insurance

Related questions

0 votes
asked Jan 17, 2020 in Agile by rahuljain1
+1 vote
asked Jun 17, 2019 in Agile by tempuser123
0 votes
asked Jan 5, 2020 in Agile by sharadyadav1986
0 votes
asked Jan 4, 2020 in Agile by sharadyadav1986
0 votes
asked Dec 5, 2020 in Agile by SakshiSharma
...