What is done during a Sprint Review Meeting?

a. Demo of the Increment

b. The team discusses the improvements that can be applied for the upcoming sprints

c. Present the Project’s performance to the Stakeholders

d. Inspect progress towards the Sprint Goal

e. Discuss the architectural and technical aspects of the project

1 Answer

0 votes
by
a. Demo of the Increment

c. Present the Project’s performance to the Stakeholders

Reasoning

The Sprint Review Meeting is conducted to demonstrate the Sprint Increment to the Stakeholders and the Customers. Another very important task in the Sprint Review Meeting is to demonstrate the Project’s performance to the Stakeholders.

The Development Team is responsible to demonstrate the Increment whereas the Product Owner is responsible to demonstrate the Project’s performance. The stakeholders and the customers are open to provide feedback which is then incorporated by the team.