What does a BurnDown Chart display?

a. Project Progress

b. Amount of remaining work with respect to time

c. The velocity of the team

d. The capacity of the team members

e. How many more items can be picked up in a Sprint

1 Answer

0 votes
by
b. Amount of remaining work with respect to time

Reasoning

A burndown chart represents the amount of remaining work with respect to the time.

The horizontal axis represents time whereas the vertical axis represents the amount of work remaining. The burndown chart is one of the several metrics that is used in Scrum to project the completion date of the project given the product backlog, team’s capacity and team’s velocity remains the same.