Who is responsible to measure the Project’s performance?

a. The Scrum Master

b. The Delivery Manager

c. The Product Owner

d. The Development Team

e. The Scrum Team

1 Answer

0 votes
by
c. The Product Owner

Reasoning

Being the customer’s voice, it is the Product Owner’s responsibility to measure the Project’s and Release performance and see if the team is on track to complete the project on time.