Project management process groups have all of the following characteristics except:

a All of the process groups are needed on all projects and all of their interactions apply to each phase of a project as well as the overall project.

b The process groups are seldom one-time, discrete events; they are overlapping activities that occur throughout the project.

c Where a project is divided into phases, the process groups are invoked as appropriate.

d The process groups are linked by the outputs they produce.

1 Answer

0 votes
by
All of the process groups are needed on all projects and all of their interactions apply to each phase of a project as well as the overall project.
Click here to read more about Loan/Mortgage
Click here to read more about Insurance

Related questions

0 votes
asked Oct 1, 2020 in PMP by SakshiSharma
0 votes
asked Sep 14, 2020 in PMP by SakshiSharma
0 votes
asked Oct 1, 2020 in PMP by SakshiSharma
+2 votes
asked Jan 21, 2020 in Data Science by sharadyadav1986
0 votes
asked Jul 2, 2020 in Python by GeorgeBell
...