The Control Costs process includes all of the following except:

a Informing appropriate stakeholders of all approved changes and associated

costs.

b Influencing factors that create changes in the authorised cost baseline.

c Developing the cost performance baseline.

d Acting to bring expected cost overruns within acceptable limits.

Answers Reference: PMBOK® Guide Section 7.4 p259

1 Answer

0 votes
by
Developing the cost performance baseline.