The risks in the Risk Register are updated as a part of each of the following

processes:

a Plan Risk Management, Identify Risks, and Perform Qualitative Risk

Analysis.

b Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk

Analysis and Monitor Risks.

c Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan

Risk Responses, Implement Risk Responses and Monitor Risks.

d Plan Risk Management, Identify Risks, Plan Risk Responses, and Monitor

Risks.

1 Answer

0 votes
by
Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, Implement Risk Responses and Monitor Risks.