Categories
5G Network
Agile
Amazon EC2
Android
Angular
Ansible
Arduino
Artificial Intelligence
Augmented Reality
AWS
Azure
Big Data
Blockchain
BootStrap
Cache Teachniques
Cassandra
Commercial Insurance
C#
C++
Cloud
CD
CI
Cyber Security
Data Handling
Data using R
Data Science
DBMS
Design-Pattern
DevOps
ECMAScript
Fortify
Ethical Hacking
Framework
GIT
GIT Slack
Gradle
Hadoop
HBase
HDFS
Hibernate
Hive
HTML
Image Processing
IOT
JavaScript
Java
Jenkins
Jira
JUnit
Kibana
Linux
Machine Learning
MangoDB
MVC
NGINX
Onsen UI
Oracle
PHP
Python
QTP
R Language
Regression Analysis
React JS
Robotic
Salesforce
SAP
Selenium
Service Discovery
Service Now
SOAP UI
Spark SQL
Testing
TOGAF
Research Method
Virtual Reality
Vue.js
Home
Recent Q&A
Feedback
Ask a Question
All of the following are true of cost plus fixed fee (CPFF) contracts, except:
Home
>
PMP
>
All of the following are true of cost plus fixed fee (CPFF) contracts, except:
Sep 14, 2020
in
PMP
Q: All of the following are true of cost plus fixed fee (CPFF) contracts, except:
a The seller is reimbursed for all allowable costs incurred performing the
contract work.
b The seller receives a fixed fee calculated as a percentage of the initial
estimated project cost.
c The fee does not change based on the performance of the seller.
d The seller receives a fee calculated as a fixed percentage of the actual
project cost.
#cost-plus-fixed-fee
#cpff
1
Answer
0
votes
Sep 14, 2020
The best answer is D
i CPFF contracts pay a fixed fee to the seller based on the initial
estimated value of the work.
ii All allowable costs are reimbursed by the buyer.
iii The only time the fee will change is if the buyer changes the scope of
the work.
Click here to read more about Loan/Mortgage
Click here to read more about Insurance
Facebook
Twitter
LinkedIn
Related questions
0
votes
Q: The cost of quality includes all of the following except:
Oct 1, 2020
in
PMP
#cost-of-quality
#quality-cost
0
votes
Q: All of the following statements concerning the project scope statement are true except:
Oct 1, 2020
in
PMP
#project-scope-statement
#project-scope
0
votes
Q: All of the following are true concerning enterprise environmental factors (EEF) except:
Oct 1, 2020
in
PMP
#enterprise-environmental-factors
#eef
0
votes
Q: All of the following statements are true about product and project life cycles except:
Oct 1, 2020
in
PMP
#project-life-cycle
#product-life-cycle
#product-and-project-life-cycle
0
votes
Q: All of the following are true concerning expected monetary value (EMV) except:
Sep 14, 2020
in
PMP
#expected-monetary-value
#evm
0
votes
Q: All of the following tools and techniques are part of processes in the Executing process group except:
Sep 14, 2020
in
PMP
pmp-tools
pmp-techniques
#pmp-tools-techniques
...