Integrated Change Control includes all of the following tools and

techniques except:

a Project management plan updates.

b Expert judgement.

c Meetings.

d A change control board to approve or reject changes.

1 Answer

0 votes
by
The best answer is A

 i Project plan updates are an output from Integrated Change Control.

 ii Expert judgement and the change control meetings, of the change

control board are the defined tools and techniques for this process.