0 votes
in PMP by
Which calculation is correct for the To-Complete Performance Index (TCPI)

based on the Estimate At Completion (EAC)?

a AC + (BAC – EV)

b (BAC - EV)/(BAC - AC)

c BAC/CPIcum

d (BAC - EV)/(EAC - AC)

1 Answer

0 votes
by
The best answer is D

 i TCPI is the projection of the future cost performance that must be

achieved on the remaining work to achieve a management goal such as

the original Budget At Completion (BAC) or a calculated Estimate At

Completion (EAC).

 ii All of these formulae use standard Earned Value Management

acronyms:

Option ‘a’ calculates EAC based on future work being performed at

budgeted rates

Option ‘b’ calculates TCPI based on BAC (the question asked for EAC)

Option ‘c’ calculates EAC based on future work being performed at the

same CPI as the completed work.

 iii For more on TCPI see:

https://mosaicprojects.com.au/WhitePapers/WP1097_TCPI_in_EVM.pdf

Related questions

0 votes
asked Feb 7, 2020 in JAVA by SakshiSharma
0 votes
asked Nov 9, 2019 in Azure by rajeshsharma
...