0 votes
in PMP by
All of the following tools and techniques are part of processes in the

Executing process group except:

a Performing activities in accordance with the project management plan.

b Managing changes to the deliverables.

c Completing the work in accordance with the defined quality framework and

specification.

d Coordinating people and resources.

1 Answer

0 votes
by
The best answer is B

 i Managing changes is part of Integrated Change Control; this is part of

the Monitoring and Controlling process group.

 ii The Executing process group consists of those processes performed

to complete the work defined in the project management plan to

satisfy the project specifications.

 iii An output from Integrated Change Control is updates to the project

management plan to incorporate approved changes.

Related questions

0 votes
asked Oct 1, 2020 in PMP by SakshiSharma
0 votes
asked Oct 1, 2020 in PMP by SakshiSharma
...