In case you receive a story on the last day of the sprint to test and you find there are defects, what will you do? Will you mark the story to ‘done’?

1 Answer

0 votes
by

A story is said to be ‘done’ only when it is completely developed, has passed QA testing, acceptance criteria ais met and is eligible to be shipped into production. So, if the story you received passes all these conditions then you can add it to the ‘done’ list. In case, if there are defects, the story is partially done and not completely done, you will have to spill it over to next sprint.