In the middle of the iteration, how does a team handle requirement changes from the customer?

1) Its not recommended to incorporate any changes during an ongoing iteration

2) Team can always take up the changes and extend iteration duration if needed

3) Team has to exchange the stories if the Scrum Master/Lead convey the criticality of the changes

4) Team may take up the changes in flight after discussing the overall impact with the Product owner

1 Answer

0 votes
by
edited by

Answer 4: Team may take up the changes in flight after discussing the overall impact with the Product owner 